A South American pharmaceutical manufacturer asked Zamann Pharma Support to help validate a new Purified Water (PW) system. On paper, the project looked sound: solid equipment and a qualified vendor.
However, the failure was strategic, not technical: no solid risk assessment supported the PW validation. Instead, the team had adopted parameters without justification and never truly challenged “worst-case conditions.” As a result, the system was validated on paper, not in reality.
This reflects a recurring global issue: companies validate equipment, not risk. Consequently, they face rework, inspection findings, delays, and budget overruns.
In this case, our team reviewed the validation, traced the failure to a weak risk assessment, and identified the gaps behind it.
Our team supports the planning, execution, and maintenance of qualification and validation activities, including IQ, OQ, and PQ, to keep GMP-regulated systems compliant and under control.
Purified Water (PW) acceptance criteria should reflect applicable pharmacopoeial requirements, the water’s intended use, and a documented quality risk assessment. TOC limits must comply with the applicable pharmacopoeial monograph, while microbial alert and action levels should consider contamination risks and system performance data. For new systems, provisional monitoring limits can be established and refined as qualification data become available. Following WHO TRS 1033, Annex 3, manufacturers should use monitoring trends to demonstrate ongoing chemical and microbiological control.
No. A flow velocity of 1 m/s is a commonly used engineering target, not a universal GMP requirement. The appropriate velocity depends on pipe diameter, system design, operating conditions, and microbial contamination risks. WHO TRS 1033 recommends maintaining turbulent circulation, using a Reynolds number above 4,000 as an example. Manufacturers should document their hydraulic design rationale and verify flow performance during qualification, particularly under minimum-demand conditions where stagnation and biofilm risks may increase.
PW performance qualification should demonstrate that the system consistently delivers water meeting specifications under scientifically justified worst-case operating conditions. These may include peak consumption, minimum recirculation flow, extended periods of low demand, sanitization challenges, and sampling at microbiologically vulnerable points of use. The testing strategy must follow a documented risk assessment rather than relying solely on vendor protocols. WHO TRS 1033 also describes a three-phase validation approach covering at least 12 months to evaluate performance across seasonal variations, supported by ongoing monitoring and periodic system reviews.